  • POWER 20-02-2015

    • Full power is supplied to Agricultural, Industrial and domestic consumers. As many as 1027 lakh units per day and 1104 lakh units per day were supplied in the month of November and December 2014  respectively as against 919 lakh units per day and 995 lakh units per day supplied in the corresponding months in the year 2013.
    • Four old units of 110 MW each at Panipat Thermal Power Plant will be replaced with 800 MW super critical Thermal Power Plant.  
    • A 800 MW super critical Thermal Power Plant will be set up at Yamunanagar.
    • Decision to launch a new programme for strengthening of power distribution system in the rural area under Deendayal Upadhayay Gram Jyoti Yojana of Government of India at a cost of about Rs 1000 crore.
    • A new programmme is being launched for strengthening of the Power Distribution System in the urban area under Integrated Power Development Scheme (IPDS) of Government of India at a cost of around Rs. 1000 crore.
    • Under the R-APDRP Programme, an investment of around Rs. 1000 crore will be made for strengthening the distribution system in 36 towns.
    • A 33 KV electricity lines of Haat and Singhana sub-station will be transferred which are passing over the residential area of Safidon city.
    • The number of transformers will be increased in towns and villages and wires of old conductors will be changed.
    • 33 KV lines and 11 KV HT and LT lines passing over the residential houses of towns of Bahadurgarh and Jhajjar will be shifted to other places.
    • A 33 KV sub-station will be constructed at Khazirabad.
    • A 220 KV sub-station will be constructed in Safidon.